Custom Rates are used in performance report saving calculations. These rates are used so the cost savings will be consistent across a time period and is not affected by baseline rates or performance rates.
Rates are combined together within a collection. Collections are used to manage how rates change over time. These collections can then be added to a project on the projects tab. The benefit of collections is that if some buildings within a project have different rates while other have the same, then a collection can be created for each unique rate then applied to the buildings that use it, without having to create the rates over and over for each building.
A custom rate is applied over a date range selected on the rate itself.
- Example
- If a rate is added for January 2022 and January 2023
- Anything before January 2022 all the way to December 2022 will use the January 2022 rate
- Anything after January 2023 will use that rate
Tech Services - Old